Request for Temporary Access/Entrance, Signboard & Temporary Fence.
Tenant should submit the following Documents to Hard Facility Management at    ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management.
  2. Undertaking Letter Application
  3. Road Opening Excavation Works Application Form
  4. M/s. ZonesCorp Approval (Erection of Temporary Fence/ Temporary Access & Project Signboard).
  5. Site Layout Plan
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request For Temporary Power Connection Works.
Tenant should submit the following Documents to Hard Facility Management at   ICAD / AAIC Offices.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.


Request For Sewer Connection Works.
Tenant should submit the following Documents to Hard Facility Management at   ICAD / AAIC Offices.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Permeant Access.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management
  2. Tenant Access Approval Application Form
  3. Road Opening Excavation Works Application Form
  4. Undertaking Letter Application
  5. Affection plan (Site Plan) Approved by M/s. ZonesCorp.
  6. Affection plan (Site Plan) Approved by M/s. ADM (Abu Dhabi Municipality).
  7. Copy of Site General Layout Approved by M/s. ZonesCorp.
  8. Copy of Site General Layout Approved by M/s. ADM.
  9. Detailed Shop Drawing of the Requested Access Showing the Existing Services, Dimensions and the Radius of Entrance will be provided by Hard Facility Management.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Completion Certificate for Sewer Connection.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management
  2. As-Built Drawings (Hard/Soft) Copies.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Completion Certificate for Permanent Entrance / Access.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management
  2. As-Built Drawings (Hard/Soft) Copies.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Telephone Connection Works.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Water Connection Works.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Permit for Permanent Water Connection
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management
  2. NOC from M/s. ZonesCorp
  3. Water Dewatering Approval From M/s. ADDC
  4. Water Meter Schedule From M/s. ADDC
  5. Undertaking Letter
  6. Road Opening Excavation Works Application Form
  7. Backfilling Check List
  8. ADDC Approved Drawing
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Permanent Electrical Connection.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
  1. Official Letter from Tenant to Hard Facility Management
  2. ADDC Approved Drawing.
  3. M/s. ZonesCorp Approval for Electrical Works in ICAD/AAIC Cities.
  4. Undertaking Letter Application
  5. Road Opening Excavation Works Application Form
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Gas Connection Works.
Tenant should submit the following Documents to Hard Facility Management at ICAD / AAIC Offices.
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Request for Sewer Water Discharge to ICAD Sewer System.
After Getting Completion Certificate From Hard Facility Management Tenant Should Submit Direct letter to M/s. ZonesCorp for Approval / Advise. (SAMPLE)
Note: All Forms to be endorsed (Signed & Stamp) by Tenant / Investor or Main Contractor.

Mechanical Excavation at ICAD/AAIC.
For Any Mechanical Excavation Tenant Must be attached Excavation Trench Entry Checklist Form with their Request (Access/Sewer/Gas/Telephone/Water).

Note: For further details/clarification's, please do not hesitate to contact with AJC HFM Enforcement Team.